The Practical Solution Public Company Limited (mai: TPS) announced on October 20, that the Win Telecom Company Limited (a subsidiary company) has completely signed a turnkey contract for a 115 KV power transmission system for the Provincial Electricity Authority with the Nakornchai Civil Work Company Limited, with a total contract value of 105 million baht (VAT included).
The scope of work is the construction contract of 115 KV system power transmission line, Cut and Turn Ratchaburi to Khao Yoi, according to the project of transmission system and distribution system development phase 1 and plan 1, with a delivery period of 365 days.