TEAMG Signs 9 New Projects in Jan-Mar 2022, Totaling THB409 Million

TEAM Consulting Engineering and Management Public Company Limited (SET: TEAMG) informed the Stock Market of Thailand on Monday that it has newly signed projects totaling THB409 million in January-March 2022 as follows; 

 

1. Construction Supervision of Khlong Prem Prachakon Drainage Tunnel from Khlong Bang Bua into the Chao Phraya River Project by the company and Geotechnical & Foundation Engineering Company Limited (GFE ; a subsidiary of the company) 

Client: Department of Drainage and Sewerage, BMA

2. Construction Supervision of Khlong Saen Saep Drainage Tunnel from Khlong Saen Saep and Khlong Lat Phrao Drainage Tunnel to Soi Lat Phrao 130 Project by the company

Client: Department of Drainage and Sewerage, BMA

3. Construction Supervision of Mahasawat Water Treatment Plant Expansion to 800,000 cu.m./day and related work (Contract SV-901) by the company

Client: Metropolitan Waterworks Authority

4. Dam Break Analysis and Emergency Action Plan of Bang Phra Dam by the company and GFE

Client: Royal Irrigation Department

5. Instrumentation for Lamsapung Dam (Main Dam) Phase 2 by GFE

Client: Royal Irrigation Department

6. Technical In- House Consultant for Bureau of Location and Design, Department of Highways by the company and TLT Consultants Company Limited (TLT; an affiliate of the company)

Client: Department of Highways

7. Survey and Design of 4-Lane Highway No.3267, Ang Thong –Bangkhamod Sub-district section by the company and TLT

Client: Department of Highways

8. Survey and Design of 4-Lane Highway No.117, Uttaradit – Phu Du section, Pa KhanunSak Yai intersection by GFE

Client: Department of Highways

9. Consulting service on the improvement and optimization of the centralized air conditioning system ( Chiller) for the office and SCADA buildings of Provincial Electricity Authority in 12 areas by ATT Consultants Company Limited (a subsidiary of the company)

Client: Provincial Electricity Authority