Right Tunnelling Public Company Limited (SET: RT) has reported eight new projects from January to March 2022, in total value of 1,896,862,429.75 Baht (including VAT) as follows:
1) Construction Project of a Drainage Tunnel of Khlong Thawi Watthana in the Bottleneck Area
Project Owner : Department of Drainage and Sewerage, Bangkok Metropolitan
Administration
Employer : Nawarat Patanakarn Public Company Limited
Project value : 1,797,575,244.50 Baht (including VAT)
Status of work : Entered into a contract
2) Construction Project of Slope Stability and Prevention of Pipeline Movement RC0460 KP.35+670
Project Owner : PTT Public Company Limited
Employer : PTT Public Company Limited
Project value : 20,321,487.61 Baht (including VAT)
Status of work : Acquired letter of acceptance and pending contract signing
3) Construction Project of Foundation Remedy of Highway No. 2013 Section 0200, Bor Pho – Khok
Ngam, Sta. 64+350 to 64+780 (LT.)
Project Owner : Department of Highways
Employer : Bureau of Highway Construction 2 (LT.), Department of Highways
Project value : 9,944,999.13 Baht (including VAT)
Status of work : Entered into a contract
4) Construction Project of Foundation Remedy of Highway No. 21 Section 0200, Phoo Kae Bridge –
Manow Whan Section, Sta. 8+015 to 8+170 (RT.)
Project Owner : Department of Highways,
Employer : Bureau of Highway Construction 11 (Lop Buri), Department of
Highways
Project value : 14,834,768.51 Baht (including VAT)
Status of work : Entered into a contract
5) Construction Project of Foundation Remedy of Highway No. 106, Section Don Chai – Huai Ya Sai,
Sta.14+060 to 14+118
Project Owner : Department of Highways,
Employer : Lampang 1 Highway District, Department of Highways
Project value : 10,379,530.00 Baht (including VAT)
Status of work : Entered into a contract
6) Construction Project of Foundation Remedy of Highway No. 333, Section 0400, Chao Phraya River
Crossing Bridge – Thanam Oi, Sta. 18+227 to 182+838
Project Owner : Department of Highways,
Employer : Nakhon Sawan 1 Highway District, Department of Highways
Project value : 18,088,000.00 Baht (including VAT)
Status of work : Bid won, pending contract signing
7) Construction Project of Foundation Remedy damaged by the flood of Highway No. 2216, Section 1
Khok Mon – Kok Kathon, Sta. 67+320 to 67+375
Project Owner : Department of Highways,
Employer : Petchabun 1 Highway District, Department of Highways
Project value : 14,909,000.00 Baht (including VAT)
Status of work : Bid won, pending contract signing
8) Pre-construction Project of Geotechnical Investigation of Den Chai – Chiang Rai – Chiang Khong
Railway – Contract 1, Section Den Chai – Ngao
Project Owner : The State Railway of Thailand
Employer : Italian-Thai Development Public Company Limited
Project value : 10,809,400.00 Baht (including VAT)
Status of work : Pending contract signing